Project Schedule

Riyadh Smart Villa — 56-week construction programme

StageWeeks 1 – 56ProgressStatus
Design & Approvals
100%Completed
Permits
100%Completed
Mobilization
100%Completed
Excavation
100%Completed
Foundation
92%In Progress
Structure
61%In Progress
MEP First Fix
24%In Progress
Envelope & Cladding
0%Planned
Finishing
0%Planned
Testing & Commissioning
0%Planned
Handover
0%Planned

Dependencies

  • Structure cannot start before Foundation reaches 90%.
  • MEP first fix depends on Structure floor-by-floor completion.
  • Finishing follows Envelope & Cladding closure.

Delayed tasks

  • Structure — 6 days behind due to steel delivery.
  • MEP first fix — at risk if structure does not recover.