Variation Orders

Change requests, their cost and their schedule impact.

All variations

Total variation value: SAR 193,900
VO NumberDescriptionReasonRequested ByCost ImpactSchedule ImpactStatus
VO-014Marble upgrade to main lobbyClient requestClientSAR 128,4004 daysUnder Review
VO-011Additional 2 parking baysMunicipality requirementConsultantSAR 86,0006 daysApproved
VO-016Relocation of MEP riserDesign clashProject ManagerSAR 42,5002 daysSubmitted
VO-009Facade lighting scope removalValue engineeringClientSAR -63,0000 daysApproved