Variation Orders
Change requests, their cost and their schedule impact.
All variations
Total variation value: SAR 193,900| VO Number | Description | Reason | Requested By | Cost Impact | Schedule Impact | Status |
|---|---|---|---|---|---|---|
| VO-014 | Marble upgrade to main lobby | Client request | Client | SAR 128,400 | 4 days | Under Review |
| VO-011 | Additional 2 parking bays | Municipality requirement | Consultant | SAR 86,000 | 6 days | Approved |
| VO-016 | Relocation of MEP riser | Design clash | Project Manager | SAR 42,500 | 2 days | Submitted |
| VO-009 | Facade lighting scope removal | Value engineering | Client | SAR -63,000 | 0 days | Approved |